Purpose

After the Sprint Review and just before the end of the Sprint, another meeting will be held, aimed at process improvement (learning lessons), which is called Sprint Retrospective.

There is a rule: we should always look for ways to improve. It does not matter how little the improvement is, there should be an improvement. This meeting is a formal opportunity for improvement, even though we do not limit our improvement to the results of this meeting. We will review (inspect) the Sprint, with regards to people, relationships, processes, and tools, and identify ways of improving them in the next Sprint.

Duration

This meeting is normally three hours for a one month Sprint. If the Sprint is shorter than one month, this meeting will be proportionally shorter.